Installation of Subsea Corrosion-Erosion Monitor (CEM) offshore India

Installation and configuration from vessel to seabed

Field case offshore India, Subsea CEM

Introduction

Håvard Pihlstrøm, one of our service engineers went to India in January 2024 for installation and configuration of one of our ClampOn Subsea Corrosion-Erosion Monitors (CEM) prior to deployment at a water depth of around 850 meter.

Functional testing of the Corrosion-Erosion Monitor

When Håvard arrived on the vessel from which installation would take place, the PLET (Pipeline and Termination) module was ready on deck. They lifted the electronics canister into place and installed it first before commencing functional testing. This functional testing and a software update took time due to a slow network connection. However, with excellent help from crew on board, the task was completed and the canister removed for safekeeping until later

Subsea CEM ready for functional testing

Subsea CEM ready for functional testing

The A-frame and PLET module

On the night of 7th January the PLET module was moved onto what is called the "A-frame", which is a large frame with hydraulics and a winch used to bring the PLET module to a vertical position prior to welding it to the pipeline. It is impressive to see a 24" steel pipe arcing all the way upwards from a depth of over 800 metres to the ship where the PLET module is welded in place.

PLET module on the A-frame where it is attached to

PLET module on the A-frame where the SS CEM is attached to

Rotating the electronic canister in place

Early on the 8th January, they finished welding and coating the pipe, and were then ready for final functional testing of the Subsea CEM. The electronics canister rotated elegantly in place, despite the Subsea CEM hanging vertically and the locking mechanism having to overcome gravity. The crew were impressed with the design

Functional testing of SS CEM - India

Final preparations before deploying the module subsea

Deployment of the PLET module and Subsea CEM

Functional testing went without a hitch and everything looked good. With a temperature of 30 degrees and a ship waiting for our engineer to complete his task, it was important to work effectively and with precision. Half an hour after he was finished, they commenced deployment of the PLET module subsea, and three hours later it was on the seabed with our Subsea CEM ready to aid safe operation.

SS CEM installed subsea, India

The Subsea Corrosion-Erosion Monitor in place

Engineer`s assessment of the installation process

"It`s exciting to experience a country like India, and working from a ship was new to me. It has been a fantastic opportunity to work on our Subsea CEM as part of a larger installation. It was impressive to see the whole process, from short lengths of pipe to completed gas pipeline 850 metres below. Final testing of the Subsea CEM was carried out while the module was vertical prior to submersion, which meant challenging working conditions and extra safety measures while installing the electronics canister. Fortunately, the test went quickly and without a hitch, and the design worked just as well vertically as it does horizontally"

Håvard Pihlstrøm - ClampOn Engineer, Field Operations

Jobs done

We thank Håvard for his efforts and look forward to more projects of this type in the future

SS CEM installation in India - Sunset

Sunset in India - Jobs done!

Field cases

  • All field cases